A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of theobstacles reported, but the timeline continues to deviate further each day with no signs of improvement.What should the project manager have done to avoid this issue?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.What should the project manager do?
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.What should the project manager have done?
A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.How should the project manager ensure project success?